How long it takes to build a shed
A steel shed goes up in less than a day once the base is ready. A made-to-order steel shed takes 10 to 12 weeks from order. A timber shed built in the garden is usually booked about 10 days ahead, and up to 10 weeks ahead in the busy season. Allow 3 to 4 days for a new slab to harden in dry weather before the shed goes on it.
From order to a finished shed, step by step, with the waits that hold a job up.
No charge and no obligation. Only one builder in your county ever sees your request.
- 10 to 12 weeksto make a steel shed to order
- 3–4 daysfor a slab to harden
- under a dayto put up a steel shed
- 4 weeksfor a section 5 answer

From order to finished
- Settle the planning. Inside the limits there is nothing to file. If in doubt, a section 5 declaration takes 4 weeks.
- Order and pay the deposit. 12% on one timber range, 50% on large steel buildings.
- Get the base plan. Several makers send exact measurements after the order. Pour nothing before it arrives.
- Lay the base. Then allow 3 to 4 days in dry weather for it to harden.
- Build day. A steel shed goes up in less than a day. Made-to-order steel takes 10 to 12 weeks to arrive.
- Fit it out. Shelving, then power from a Registered Electrical Contractor.
Price your shed
Three taps and your county, and the price shows as you go. Your name and number come last, and only if you want a builder to price it.
A steel shed, about 3 × 3 m, behind the house: €1,110 to €2,990, built on site.
How the price is worked out
The figure is what a shed of that kind and size costs in Ireland now, delivered and put up on your site by the seller's own crew. Where prices differ, you see the lowest and the highest. A steel garage starts at 6 × 3 m, so smaller sizes show where it starts. Block-built sheds are priced after a visit. The base, electrics and any windows beyond the standard ones are not in any figure, because they depend on your site. Ask whether a quote includes VAT, and at which rate. Use it to plan with. It is not a quote: a builder prices yours after seeing where it goes.
Timing by kind
Steel, from stock
Less than a day on site
Booked once the base is ready.
Steel, made to order
10 to 12 weeks
From order to the build day, on one maker's current times.
Timber, built on site
10 days to 10 weeks
How far ahead the build is booked, quiet season to busy season.
Block-built
Stage by stage
Foundation, walls, roof and render, each waiting on the last.
Large steel building
Scheduled from a photo
Send a photo of the finished base and the install date is confirmed.
What holds a job up
- A base that is not ready, not level or not hard yet.
- Wind on the day. Crews will not put up sheets in high winds, and a build can be moved at short notice.
- No side access. A timber shed then has to be cut down first, at €55.
- A planning question left until after the order.
- Changing the order once it has gone into the factory.
Other sheds and guides
Bases and slabsThe concrete a steel shed bolts to, and the blocks a timber shed sits on.
Steel shedsSteel sheets on a galvanised frame, put up in a day, priced by size.
Timber shedsBuilt on blocks in the garden, with prices from 6 × 4 ft to 20 × 10 ft.
Block-built shedsConcrete block walls on a foundation, rendered to match the house.
VAT on a built shedWhen a shed is taxed at 13.5% and when at 23%.
Steel garagesRoom for a car, from 6 × 3 m, and the sizes that fit the 30 m² limit.Questions before you build
How long does a steel shed take to put up?
Less than a day on a ready base.
How long is the wait for a made-to-order steel shed?
10 to 12 weeks from order on one maker's current times.
How long before a shed can go on new concrete?
About 3 to 4 days in dry weather. Full drying takes up to 30 days.
Can a shed be put up in wind?
Not a steel one in high winds. The sheets catch the wind, and crews move the build to a calmer day.
How long does a section 5 take?
The council has 4 weeks to answer, or 3 weeks from any further information it asks for.
Everything on this site
Sheds
Building one

Your shed, priced before anyone calls
Pick the kind of shed, a size and where it goes. A firm quote comes from a single shed builder in your county, once you ask for one.
